Concrete Calculator

Estimate the volume of concrete needed for a rectangular slab, footing, or pad, including a wastage allowance.

The formula

Volume = length × width × thickness (all converted to the same unit). A wastage percentage is added on top to account for uneven ground, spillage, and formwork variance — concrete is typically ordered a little over the exact calculated volume rather than under, since running short mid-pour is far more disruptive than having a small surplus.

Worked example

A 6m × 4m slab at 10cm thick: 6 × 4 × 0.10 = 2.4 m³ before wastage. With a 10% wastage allowance, that's 2.64 m³ (about 3.45 yd³) of concrete to order.

Why order extra

  • Ground is rarely perfectly level, so actual thickness varies across the slab
  • Some concrete is lost during mixing, transport, and pouring
  • Running short mid-pour can create a weak seam where the pour is interrupted

Frequently asked questions

How much wastage allowance should I use?

10% is a common default for a straightforward slab. Uneven ground, complex formwork, or a first-time DIY pour often justify 15-20% instead, to avoid running short.

Does this account for reinforcement (rebar or mesh)?

No — this calculates the concrete volume only. Rebar or mesh reinforcement is planned and ordered separately based on your project's structural requirements.